Legend
|
|
A.1
|
Source for potential sponsors
|
A.2
|
Prepare essential material
|
A.3
|
Source for manpower
|
A.4
|
Confirm sponsor list
|
B.1
|
Contact potential sponsor
|
B.2
|
Close deal
|
C.1
|
Update sponsor on SLL
|
C.2
|
Check material/money received
|
C.3
|
Invite representative to SLL opening day
|
D.1
|
Activity
|
No. of weeks
|
Proceeded by
|
A.1
|
3
|
|
A.2
|
6
|
A.1
|
A.3
|
3
|
A.1
|
A.4
|
2
|
A.3
|
B.1
|
14
|
A.4
|
B.2
|
7
|
B.1
|
C.1
|
Till opening day (2014)
|
B.2
|
C.2
|
10
|
B.2
|
C.3
|
2
|
C.2
|
D.1
|
-
|
C.3
|
Thus, here is the AON table,
The earliest finish time : 44 weeks
The latest finish time: 46 weeks
There will be a float of 2 weeks in case of any unforeseen event happen.
Next would be the gantt chart,
Date to start on 23 April 2012 or maybe next week on 30 April 2012
We will be contacting the sponsors maybe around 9 July to 12 October (14 weeks)
Then we could close the deal with sponsor around 15 October to 30 November (7 weeks)
Next update the sponsor till the opening event of SLL